Specifications include, but are not limited to: • Provide precast concrete reinforced concrete bridge deck panel with integrated concrete curbs • Deck shall support legal highway loads with no additional reinforcement required • Integrated concrete curbs with scuppers poured in a single pour as part of the deck panel are required (separate curbs attached with fasteners are not allowed) • Minimum total running surface width between curbs shall be 12’ width inside curbs. • Panels shall be 8” thick. • Individual pieces shall not weigh more than 8,000 lbs • Concrete shall be 4,500 psi at 28 days • Concrete shall cure 7 days prior to delivery • An engineer’s stamp may be required (please show this cost separately) • Prices shall include transportation to the project site at the outlet of Seboeis Lake approximately 22 miles north of Brownville Junction. • All pieces shall have cast in lift hooks.