Specifications include, but are not limited to:. The scope of work includes pipe lining for 880 linear feet (LF) of 12” corrugated metal pipe (CMP) and 58 LF of 15” CMP. A 213 LF 18” CMP is included in the scope of work, as well. We believe a spot repair may be adequate to address the 18” pipe, but are also asking for the full lining cost for this pipe segment separately in the event that action is determined to be necessary. Work includes not only the installation of the pipe lining, but also cleaning, repairing and preparing the existing pipe prior to CIPP installation; bypass pumping of flow, if necessary; traffic control; performing required materials sampling and testing; performing video inspection of the completed lining; cleanup of the project area; and furnishing all labor, tools, equipment, and incidentals necessary to complete the work.