The project consists of the furnishing, construction and installation of new Granular Activated Carbon (GAC) Adsorption/Filtration Systems at five (5) locations; Construction of Filter Buildings, Building Additions, Chlorination Equipment, Underground and Above ground Piping, Valves and Fittings, Demolition of Existing Facility Infrastructure, Various Site Improvements including Upgrade of Existing Driveway, Erosion and Sedimentation Controls and Site Restoration, including Grading, Seeding, Concrete Work, Curbing and Paving. Electrical Construction includes upgrades to existing electrical service supply and installation of circuit breakers, transfer switches, transformers, motor starters, conduit and wiring and lighting, instrumentation and SCADA system modifications and associated work. Mechanical (HVAC) Construction includes supply and installation of ceiling fans, louvers, heaters, dehumidifiers, duct work and accessories.