** FOR RESEARCH PURPOSES ONLY **
The work includes partial demolition and new construction required to fully reconfigure and expand existing administrative area located on western side of south and south center bays in Building B107. Project scope includes new wall partitions, doors, ceilings and flooring along with coordination of mechanical, electrical and fire protection disciplines to meet all program requirements. Existing modular office located in the B/25 column grid location is to remain as part of the expansion design layout and incidental related work.
In addition, brand name or equal references are necessary to effectively communicate structural interior colors and finish selections to effectively communicate the design intent of the interior of the facility to ensure an aesthetically pleasing, professional environment. Specific brand name structural finish materials are listed.
FLOORING
LVT-1 LUXURY VINYL PLANK ARMSTRONG BIOME ST263 SAVANNAH MONSOON
WALLS (PT-1 thru PT-4 17,145 SF)
PT-1 PAINT BENJAMIN MOORE EGGSHELL
PT-2 PAINT BENJAMIN MOORE SEM-GLOSS
PT-3 PAINT BENJAMIN MOORE EGGSHELL
PT-4 PAINT BENJAMIN MOORE EGGSHELL
DOOR/SIDELITE FRAMES
HM Frames PAINT BENJAMIN MOORE
CEILING
ACT-1 ACOUSTICAL TILE ARMSTRONG ULTIMA HIGH NRC 1941A
MISCELLANEOUS
WB-1 RUBBER BASE JOHNSONITE 4" H Base
CG-1 CORNER GUARDS INPRO CORPORATION SURFACE MOUNT 3" WING
TRS-1 TRANSITION STRIPS SCHLUTER SYSTEMS VARIES
PLAM-1 PLASTIC LAMINATE WILSONART WALL CABINETS
PLAM-1 PLASTIC LAMINATE WILSONART BASE CABINETS
SS-1 Solid Surface CORIAN COUNTERTOP