Specifications include, but are not limited to: Green Street – From Church Street gutter line to East 1st Avenue gutter line– full road width. Approximate length = 754’. Approximate road width = 20’. Approximate total area = 1,657 square yards. Base repair estimate = 360 square yards. • Provide all necessary traffic controls for complete project. • Saw cut / mill pavement joints (all locations including driveways if applicable). • Mill road full partial 2-inches – minimum depth. Mill additional depth, if necessary, to remove any roadway surface irregularities. • Malvern Borough shall adjust all manholes if necessary. • Complete base repair as directed by the Borough representative. Base repair shall consist of the following: o Remove existing asphalt, stone and / or soil in locations specified by the Borough representative up to an additional four (4) inches. This shall occur after the milling operation (to permit the evaluation of the road surface by the Borough) for a total depth of six (6) inches from existing roadway elevation. ▪ Compact subbase / subgrade material with appropriate equipment. ▪ Install four (4) inches of superpave base material in one (1) lift. ▪ Estimated area of base repair = 360 square yards. Paid on a unit price basis. • Sweep and Tack Coat roadway surface prior to paving. • Deliver and Place Superpave Asphalt Mixture Design, HMA Wearing Course, PG 64-22, 0.3 to 3.0 million ESAL’s, 9.5 mm mix, 2.0” compacted depth, SRL H. • Seal all joints, edges and utilities. • Pavement joints to existing asphalt which are to remain may be milled as long as milling operation provides a clean straight connection. If unacceptable, the Borough may require the pavement joint to be saw cut.