he work includes the installation of 263 square yards of full depth pavement which includes excavation, installation of 6" compacted subbase material, Bituminous Concrete Base Coarse: Superpave Asphalt Mixture Design, HMA Base Corse, PG64-22, 0.0 to 0.3 Million ESAL's, 25.0mm mix, 3" Depth, SRL-L, Bituminous Tack Coat: Emulsified asphalt conforming to PDT Section 460. and Wearing Course: Superpave Asphalt Mixture Design, HMA wearing Corse, PG64-22, 0.0 to 0.3 Million ESAL's, 9.5mm mix, 1 1/2" Depth, SRL-L. The project also includes the installation of 1,759 square yards of pavement overlay which includes Bituminous Tack Coat, Wearing Course: Superpave Asphalt Mixture Design, HMA wearing Corse, PG64-22, 0.0 to 0.3 Million ESAL's, 9.5mm mix, 1 1/2" Depth, SRL-L,. Incidental construction includes the replacement of 6 pole lights on existing light poles, the replacement of 2 wall pack lighting units, installation of 2 new all pack lighting units, and line painting