The Work to be done under this Contract consists of the following in Washington County located within the Urban Road Maintenance District : A. Implement temporary traffic control and temporary pollution control measures; B. Trim vegetation adjacent to and above the roadway related to contract operations; C. Perform approximately 38,000 SY of 1.5" Cold Plane Pavement Removal; D. Perform approximately 22,200 SY of 3" Cold Plane Pavement Removal; E. Perform approximately 6,000 SF of 3" Asphalt Concrete Pavement Repair; F. Place approximately 7,300 Tons of Level 2, ½” Dense ACP on Washington County roads; G. Replace traffic signal loops; H. Place approximately 20,000 FT of thermoplastic; I. Place pavement markings as required; J. Adjust utilities; K. Additional and incidental Work as called for by the Specifications; L. This project will also include Pavement repairs to be completed in Spring of 2026 which are being identified at a later date.