I. PHASE 1 1. INCLUDES ALL WORK IN ROOMS 102, 103, 104, 105, 106, 116, 119, AND 120. REMOVE ALL FURNITURE AND ITEMS ON THE WALLS, SAFELY STORE FOR REINSTALLATION EXCEPT AS NOTED BELOW, 2. IN COURTROOM 115, REMOYE THE LOW WALL BETWEEN 115 AND BENCH 114. REMOVE ALL LOOSE FURNITURE INCLUDING, ITEMS ON THE WALLS AND SAFELY STORE FOR REINSTALLATION AT THE COMPLETION OF PACKAGE 2. 3. IN STAFF ROOM 106, RELOCATE THE 6 WORKSTATIONS, FILE CABINETS, AND RELATED OFFICE FURNITURE INTO COURTROOM 115. SET UP WORKSTATIONS IN A CONFIGURATION APPROYED BY OWNER INCLUDING, CONNECTING ANY POWERED PANELS TO ELECTRICITY. COORDINATE WITH OWNER'S LOW VOLTAGE CONTRACTOR AND STAFF, RELOCATE ITEMS ON THE WALLS AS DIRECTED BY OWNER SAFELY STORE ANY ITEMS NOT RELOCATED FOR REINSTALLATION.