Dock 3 work: Demolish existing pedestals from floating docks. Demolish existing power cables from existing panel to all pedestals. Demolish existing panel and service feeder. Provide new electrical service Panel 3 and associated metering equipment. Coordinate with Brandy Gwynn of Central Lincoln PUD for all utility work. Provide all required raceways, conductors, cables and means of support. Install new pedestals to be furnished by the Port of Newport. Provide emergency disconnects IAW NEC 555.36 Provide permanent safety signs IAW NEC 555.10 Dock 5 work: Demolish existing pedestals from floating docks. Demolish existing power cables from existing panel to all pedestals. Demolish existing panel and service feeder. Provide new electrical service Panels 5A and 5B and associated metering equipment. Coordinate with Brandy Gwynn of Central Lincoln PUD for all utility work. Provide all required raceways, conductors, cables and means of support. Install new pedestals to be furnished by the Port of Newport. Provide a new service feeder and disconnect to existing fuel dock mounted on support means approved by the Harbormaster. Provide emergency disconnects IAW NEC 555.36 Provide permanent safety signs IAW NEC 555.10 Contractor is responsible for subgrade construction on City sidewalk. Contractor shall make cuts and patches to concrete in accordance with City requirements. Provide new grounding electrode systems. Contractor is responsible for the timely and legal disposal of all materials removed as a part of this project. Contractor shall allow Port of Newport personnel to salvage spare parts from demolished pedestals before final disposal.