1. Design, procure, install, and test all new fuel tank system and components as described herein. The Contractor will be responsible for all necessary permits and approvals. Provide all equipment, materials, labor and incidental work necessary to complete the project. 2. Contractor will comply with all OSHA, EPA, SPCC, DEQ AST, UL standards and safety guidelines. 3. Power wash, clean and sand the exterior tank surfaces and ladders on three (3) existing above ground fuel storage tanks. 4. Remove dirt and rust by air sanding exterior surfaces, tanks and ladders. 5. Supply and apply one (1) coat of Rodda Barrier Rust 3 inhibited primer to the exterior surfaces of the three (3) tanks. 6. Supply and apply one (1) coat of High Solids Polyurethane gloss stock white coating to the exterior surface and top of the tank. 7. Apply one (1) coat of Sherwin Williams Corathane Moisture Cure mill white to the exterior surfaces of the three (3) tanks. 8. Apply one (1) coat of Sherwin Williams Safety Yellow on tank top safety rails.