Specifications include, but are not limited to: 1 General Conditions 2 Removal and Salvage of Existing Transformers 3 Removal/Demo of Existing Cable Risers and Associated Equipment 4 Demo of Existing 15kV Breaker Foundations 5 Expansion of Transformer Foundation T2B 6 Installation of Transformer Oil Containment System 7 Installation of Breaker Foundations 8 Installation of Owner Supplied Disconnect Switches 9 Installation of Owner Supplied Breakers and Breaker Relay 10 Procurement & Installation of Below Grade Conduit and Grounding 11 Procurement & Installation of Above Grade Conduit and Grounding 12 Procurement & Installation of Bus, HV Conductor, and Fittings 13 Electrical Testing for All Equipment (Excluding Breakers) 14 Electrical Testing of Breakers