1. General Fire Suppression Items: a. All items listed in General Trade Package. b. Trade Partner is responsible for coordination of all Architectural Detail Coordination. c. NOTICE: To maintain project completion date, blocks in various areas will be phased concurrently. Trade Contractor will be required to provide multiple crews, equipment, material, and the leadership required to work in areas concurrently as shown in the project schedule. d. This is an all-inclusive trade package to include all materials, labor, and equipment to furnish and install scope as indicated on contract documents. Any trade specific items shall be included whether listed or not. e. Furnish and installcomplete, tested and ready for use wet pipe automatic sprinkler system as described in these Specifications. Provide new fire service and risers inside the building complete with all necessary flow switches, alarms, etc. to comply with NFPA 13 and all applicable local codes.