Specifications include, but are not limited to: Perform large diameter storm sewer condition assessment services, manhole inspections, and complaint/work order history where necessary. The work is generally anticipated to include the following steps: Perform a detailed review of the existing information pertaining to the project area and assemble a field work plan as detailed in Tasks A3 and A4. Conduct a field survey and locate all pertinent storm structures as detailed in Tasks A5 and A10. Conduct storm sewer assessment services for the large diameter sewers identified within the project area in accordance with Tasks A5 through A8. Conduct manhole inspections as detailed in Task A9. Complete and submit to the City any necessary Piping Ambiguity Records (PARs) and/or Manhole/Structure Inventory Update Sheets (MSIUSs) as detailed in Task A3. Data shall then be submitted to the City in a Technical Memorandum as detailed in Task A11.