WORK TO BE ACCOMPLISHED Work to be completed includes, but is not limited to the following items: 1. Contractor shall provide all labor, materials and equipment and complete the following: A. Demolition: i. Remove 2” of the top cap of existing asphalt on POV parking lot and access drives, (approximately 7,668 Sq. Yds). See the owner’s representative and the attached map (Appendix 1). ii. Remove any existing concrete parking blocks and save them for re-use. B. Installation: A. In areas where demolition of asphalt transpired (see paragraph SW III.1.A.i.). Install approximately 7,668 Sq. yds of 2” topcoat of asphalt. i. Apply the proper tack coat. ii. Use #448 type 1 asphalt materials (PG64-22). iii. Roll to a smooth finish. iv. New asphalt needs to follow existing grade and drain properly to all existing drains. B. Striping of new parking lots. i. Striping shall be one consistent color, semi-permanent, reflective traffic paint with reflective glass beads to enhance visibility. ii. Parking spaces will be striped, white, except at the end of each row of parking or at handicapped accessible aisles. These lines will be painted yellow. All crosswalks, no parking areas and access walks will be striped in yellow