Specifications include, but are not limited to: 1.1 This project will provide a complete set of construction drawings for two sidewalk connections: a 625 feet connection on the east side of Avery Road north of Tara Hill Drive; and a 450 feet connection on the east side of Avery Road north of Wynford Drive. 1.2 10 foot minimum offset between edge of sidewalk and pavement 1.3 All trees (3 inch caliper and above) and stumps will be surveyed in the project area identifying diameter, type, and health of tree. 1.4 Sidewalk alignment (horizontal and vertical) and design elements will be based on the City of Dublin Standard Construction Drawings and engineering best practices. 1.5 Consultant will obtain existing public & private utility information and coordinate relocations if necessary. 1.6 Consultant is required to coordinate the detailed design of the project with all public and private utilities within the project area. Consultant shall submit progress plans to utility providers for their comment and coordinate any relocation of utilities with the utility companies and the City of Dublin that may be necessary. 1.7 The City will provide available roadway and public utility plans in the project area. Consultant will provide field surveying, with a minimum of 1 ft. contours in the design plans, from the center of Avery Road to 30 ft. beyond existing right-of-way. 1.8 Perform detailed design of sidewalks, driveway crossings, and driveway connections to Avery Road. 1.9 Perform storm drainage review and design storm drainage facilities as necessary for storm runoff. 1.10 Property impacts: An estimate of five (5) properties are expected to have various right-of-way and easement impacts. The sidewalk connections will require acquisition of approximately 10 feet right-of-way from the Avery Road properties. 1.11 Consultant will prepare 8.5x14 legal descriptions and 8.5x14 legal exhibits for right-of-way acquisitions and for temporary construction easements in City of Dublin format. 1.12 Consultant will prepare five individual property right-of-way exhibits in City of Dublin format, either 8.5x11 or 11x17. 1.13 Consultant will meet or exceed FCEO requirements for recording right-of-way acquisitions. 1.14 Consultant to provide project survey control, set permanent benchmarks, and set right-of-way pins as required. 1.15 The NOI Permit and Post BMP treatments are not required for this project. 1.16 Consultant to follow all City of Dublin, City of Columbus, and ODOT specifications (in order) for design specifications. Project improvements shall be ADA and PROWAG compliant. 1.17 Any lane, shoulder, or ramp closures will be performed in accordance with the current Temporary Traffic Control Manual and the Ohio Manual of Uniform Traffic Control Devices. 1.18 If authorized, a total of four non-destructive test holes, not to exceed 8 ft. in depth, may be required at conflicts with underground facilities and proposed storm sewers. 1.19 Geotechnical subsurface investigation will not be required. 1.20 Consultant shall prepare an Erosion and Sediment Control Plan to meet all City of Dublin and OEPA requirements. 1.21 Meetings: Kick-off meeting (in-person), plan submittal comment disposition meetings (3), plus two (2) additional in-person meetings.