Specifications include, but are not limited to: Task 1 Environmental and Project Screening: 1. Conduct an on-site meeting with the IRT and DMS to discuss proposed mitigation plan and obtain concurrence on planned work and crediting. Document and distribute site visit through notes and receive approval via communication from IRT (e-mail or letter). 2. Follow procedure from most recent DMS and FHWA ‘Environmental Screening and Documentation Guidelines for DMS Projects’ for compliance with environmental laws and regulations. This screening tool and associated documentation must be reviewed and approved by DMS and FHWA to meet categorical exclusion requirements and demonstrate project will not have a significant environmental impact. 3. If applicable, provide a signed and dated DMS Full Delivery Landowner Authorization form prior to postcontract site visit in accordance with USACE requirements. 4. If applicable, satisfy the public notification process in accordance with USACE requirements.