A. This equipment will be prepurchased by the Owner and furnished to the successful Contractor after award for expediting delivery and installation as if the Contractor purchased the equipment directly. B. Owner will make available manufacturer provided shop drawings of Owner prepurchased equipment for review by the Contractor. Contractor shall review shop drawings to ascertain that Contractor has included necessary labor and materials to install equipment and complete system it serves. C. Contractor shall be responsible for arranging/coordinating delivery of Owner prepurchased equipment and all other related logistics and activities. This includes directing the delivery truck to the jobsite, coordinating the date and time of delivery, and receipt of the equipment at the jobsite. Manufacturer is responsible for equipment until it is unloaded at the jobsite by the Contractor. D. Contractor shall install Owner prepurchased equipment and all appurtenances. This shall include, but not be limited to; unloading, rigging and setting equipment in place, making connections, starting, testing and installing equipment in accordance with manufacturer's recommendations, and maintaining equipment until such time as project is accepted by Owner. Perform all work and provide materials and connections for Owner furnished equipment in accordance with drawings and scope of work under all related specifications. E. The following summarizes the general responsibilities of the equipment manufacturer: 1. Provide shop drawings and submittal data. 2. Manufacture and delivery of equipment including coordination of exact delivery date and supervision of rigging, unloading, and setting. 3. Lead equipment check-out, testing, and start-up process and submit report(s). 4. Provide touch up paint. 5. Provide O&M documentation. 6. Provide Owner training and participate in commissioning process.