LOW-VOLTAGE SWITCHGEAR A. This equipment will be pre-purchased by the Owner and assigned to the successful Contractor after award. B. Owner will make available shop drawings of Owner pre-purchased equipment for review. Contractorshall review shop drawings to ascertain that Contractor has included necessary labor and materials to install equipment and complete system it serves. C. Contractor shall be responsible for arranging/coordinating delivery of equipment and all other activities as if the Contractor purchased the equipment directly. This includes directing the delivery truck to the jobsite, coordinating the date and time of delivery, receipt/unloading of the equipment at the jobsite. D. Contractor shall install equipment and all auxiliaries as though Contractor had purchased equipment. This shall include, but not be limited to; rigging and setting equipment in place, making connections, starting, testing and installing equipment in accordance with manufacturer's recommendations, and maintaining equipment until such time as project is accepted by Owner. Perform all work and provide materials and connections for Owner furnished equipment in accordance with drawings and scope of work under all related specifications. E. After completion of equipment installation, assemble equipment shop drawings, operating/maintenance instructions and part lists into the Contractor's project operation/maintenance manuals. F. The following summarizes the general responsibilities of the electrical equipmentsupplier: 1. Provide shop drawings and submittal data 2. Manufacture and delivery of equipment including coordination of exact delivery date and supervision of rigging, unloading and setting. 3. Lead equipment check-out, testing and start-up process 4. Provide Owner training 5. Provide O&M documentation Please see attached Scope of Work SWITCHBOARDS A. This equipment will be pre-purchased by the Owner and assigned to the successful Contractor after award expediting delivery and installation. B. Owner will make available shop drawings of Owner pre-purchased equipment for review. Contractorshall review shop drawings to ascertain that Contractor has included necessary labor and materials to install equipment and complete system it serves. C. Contractor shall be responsible for arranging/coordinating delivery of equipment and all other activities as if the Contractor purchased the equipment directly. This includes directing the delivery truck to the jobsite, coordinating the date and time of delivery, receipt/unloading of the equipment at the jobsite. D. Contractor shall install equipment and all auxiliaries as though Contractor had purchased equipment. This shall include, but not be limited to; rigging and setting equipment in place, making connections, starting, testing and installing equipment in accordance with manufacturer's recommendations, and maintaining equipment until such time as project is accepted by Owner. Perform all work and provide materials and connections for Owner furnished equipment in accordance with drawings and scope of work under all related specifications. E. After completion of equipment installation, assemble equipment shop drawings, operating/maintenance instructions and part lists into the Contractor's project operation/maintenance manuals. F. The following summarizes the general responsibilities of the electrical equipment supplier: 1. Provide shop drawings and submittal data. 2. Manufacture and delivery of equipment including coordination of exact delivery date and supervision of rigging, unloading and setting. 3. Lead equipment check-out, testing and start-up process. 4. Provide Owner training. Provide O&M documentation.