1. COORDINATE ALL DEMOLITION WITH THE INFORMATION PROVIDED IN THIS SET OF DOCUMENTS. 2. ALL MATERIAL TO BE DEMOLISHED AND REMOVED SHALL BE DISPOSED OF AS APPROVED BY UNIVERSITY OF NC AT CHARLOTTE STANDARDS AND LOCAL ORDINANCE AND CODES. 3. THE EXISTING AREAS TO REMAIN SHALL BE PROTECTED. ALL DAMAGE RESULTING FROM WORK IN THIS CONTRACT SHALL BE RETURNED TO ITS ORIGINAL STATE. CAREFULLY DISMANTLE AND REMOVE MATERIALS SHOWN ON PLANS TO BE DEMOLISHED. NOTIFY ARCHITECT PRIOR TO CONSTRUCTION OF ANY DEMOLITION WORK THAT MAY DAMAGE THE INTEGRITY OF ANY MATERIALS WHICH ARE TO REMAIN AS EXISTING. 4. THE PREMISES IN WHICH WORK IS BEING PERFORMED SHALL BE KEPT CLEAN AT ALL TIMES. 5. EXISTING CONCRETE SLABS INTENDED TO REMAIN SHALL BE REPAIRED AND FLOATED LEVEL W/ SURROUNDING SLABS AND PREPARED TO RECEIVE NEW FINISH. 6. COORDINATE OWNER WALK THROUGH TO IDENTIFY ALL ITEMS TO BE SALVAGED FOR THE OWNER'S RE-USE. INCLUDING BUT NOT LIMITED TO DOORS, FRAMES, HARDWARE, PLUMBING AND ELECTRICAL DEVICES AND FIXTURES, EQUIPMENT, FRAMED DOCUMENTS, SIGNS, ART, ETC. REMOVE ITEMS THUS IDENTIFIED AND GIVE TO THE OWNER, OR STORE FOR RE-USE PER OWNERS DIRECTION. 7. REMOVE ALL CONDUCTORS, CONDUIT AND BOXES BACK TO PANEL IN RENOVATED AREA REMOVE ALL RELATED STRAPS AND HANGERS - RE: ELECTRICAL DRAWINGS FOR MORE INFORMATION. 8. REMOVE ALL PLUMBING FROM RENOVATED AREA TO NEAREST JUNCTURE WHERE THE LINE IS STILL USED AND CAP. REMOVE RELATED UNUSED STRAPS AND HANGERS, RE: PLUMBING DRAWINGS FOR MORE INFORMATION. PLUMBING LINE SERVING OTHER AREAS SHALL BE KEPT. CONTRACTOR IS TO VERIFY PLUMBING LINES PRIOR TO DEMOLITION. RE: PLUMBING DRAWINGS FOR MORE INFORMATION. 9. REMOVE ALL HVAC DUCTWORK IN RENOVATED AREA TO NEAREST JUNCTURE WHERE THE DUCT IS STILL IN USE AND CAP AS REQUIRED. REMOVE ALL RELATED STRAPS AND HANGERS. RE: MECHANICAL DRAWINGS FOR MORE INFORMATION. 10. DURING CONSTRUCTION, MAINTAIN NEGATIVE AIR PRESSURE ON CONSTRUCTION ZONE WHILE MAINTAINING POSITIVE PRESSURE ON THE NON-CONSTRUCTION ZONE