Work for Contract No. 1-- General Construction will consist of furnishing all materials, equipment, and labor necessary for the installation of approximately 10,225 linear feet of DR-18 C900 8" PVC water main, line valves, and fire hydrants, including all associated excavation, backfill, fittings, appurtenances, water services, clearing, paving, disinfection, landscaping, testing, connections to existing water system, demolition of existing piping, and thrust restraint, all as further detailed in the plans and specifications. This contract also includes construction of a booster pump station and the exterior site work for the Water Storage Tank, including all associated exterior piping, stormwater drainage utilities, control panels (furnish only), flow meters, transducers, electrical kiosks (structure only), chemical feed sheds and chemical feed systems, excavation, backfill, concrete foundations, concrete vaults, access roads, thrust restraint, clearing, and restoration, all as further detailed in the plans and specifications. Work for Contract No. 2 — Water Storage Tank will consist of furnishing all materials, equipment and labor necessary for the installation of a potable water storage tank, as shown and specified. Work for Contract No. 3 — Electrical will consist of installing electric services to the booster pump station and tank site, a telephone service to the booster pump station, lighting, power circuits, the telemetry system, installing control panels associated with mechanical and process equipment, furnishing and installing all additional control equipment, furnishing and installing control wiring, and furnishing and installing a standby generator at the pump station, including all necessary wiring, conduits, grounding, bonding, panelboards, automatic transfer switches, circuit breakers, and raceways, as shown and specified.