The work of this project is separated into a number of Bid Packages, of which Package
"General Trades" is the portion of work belonging to this Contractor. The Contractor will
provide a final lump sum cost proposal for the "General Trades" that will include the work
defined herein.
a. GENERAL TRADES
1) Provide the necessary materials, labor, equipment, and supervision to perform
the "General Trades" work as indicated in the Division of Work of this Section.
2) Provide and utilize the necessary equipment to perform the work in a safe and
expeditious manner.
b. Perform the work under lump sum contract with Chemung County, Owner. Furnish all
labor, materials, tools, equipment, supervision, layout, delivery, trucking, shop
drawings, submittals, as-built drawings, etc. necessary to complete the work
described in Division of Work for this Contract, whether specified above or not.
2. The following requirements apply to all bid items. these must be included in bidding any or
all of the bid items.
a. All existing conditions must be verified in the field. The Owner takes no responsibility
for actual conditions found deviating from the drawings. If existing condition interferes
with Contract Work, Contractor is responsible to eliminate the condition
DIVISION OF WORK
1. Furnish and install all labor, material, supervision, engineering, administration, project
management, equipment, layout, deliveries, trucking, hoisting, supplies, mock-ups,
rigging, shop drawings, submittals, and all other items related and required to complete all
Work in accordance with the Contract Documents and all applicable codes, laws, and
regulations having jurisdiction.
2. The Contractor represents they have expertise in the performance of work for this trade
and assure all systems to be complete, functional, and installed in accordance with the
best practices consistent with premium quality material and workmanship. The Scope of
Work includes, but is not limited to the following:
a. All work shown and described in the following drawing Series: “CS”, "CN", and “A”, of
the drawing set entitled “Elmira Corning Regional Snow Removal Equipment (SRE)
BuildiRoof Replacement”
b. All work required and described in the following Specification Sections:
1) Volume 1 in its entirety [(Bidding Requirements, Proposal, Contract Forms, FAA
General Provisions and Forms, FAA Supplemental General Provisions (SGP),
and Division 01 General Requirements (all Specifications)].
2) All Site/Civil Specifications sections starting with "C", "M", and "S".
3) Division 7 - Thermal and Moisture Protection in its entirety.
c. The work associated with this contract involves working in the airport, which will
remain operational during the project. Extreme care must be taken so that the
existing airport operations are not impacted. Any work that may affect the current facility operations will need to be scheduled and approved prior to commencing work
d. Extreme care is to be taken to avoid any unplanned interruptions to the existing
facilites operations. Any work to be performed that may impact the operations of the
facility will be done on a planned basis utilizing off-shift and weekend hours at the
cost of Contractor.
e. All equipment and materials, fuel, oil, and repairs for equipment utilized in this scope
of work.
f. Provided daily clean-up of work, staging areas, and private and public roads. Place
debris in containers provided by Contractor. Any hazardous debris shall be handled
in strict accordance with all laws and regulations by Contractor.
g. Contractor is responsible for all scaffolding, fall protection, hoisting, and any other
labor, materials, or equipment necessary to complete this scope of work.
h. All labor and material to provide weather protection required to perform the work and
protect the finished work within this scope.
i. Maintenance of all staging areas as it pertains to this scope of work.
j. Contractor must comply with all Airport and Contractor's own site specific safety
policies.
k. Contractor is responsible for all permits/inspections required to perform this scope of
work.
l. Contractor is responsible for all items related to the scheduling, coordination, safety,
submission of a lift plan, and planning of crane operations to complete all contract
work for this project.
m. Contractor is responsible for cleanup, removal, and cost of any hazardous materials,
oil contaminated materials, spills, or leaks.
n. Contractor must protect their own work as well as the work of others when performing
this scope of work.
o. Contractor will be required to correct all defective work as directed.
p. Contractor is responsible for adhering to all OSHA requirments for personal and job
site safety pertaining to their specific scope of work.
q. Contractor will provide all necessary trash removal for the site.
r. Contractor will be required to submit a sequence and logistics plan for any activities
and locations that may affect visibility of the existing apron, taxiways, runways, etc.
for review and approval by the Airport and the FAA prior to the start of work.
s. The work in this contract is not limited to any particular drawings. All drawings should
be reviewed to determine the scope of this contract.