1 Milling 2 inch 28,400 SY 2 Hot Mix Asphalt 9.5M64 Surface Course, 2” Depth 3,700 TON 3 Construct 6” Base 19M64 Mix 900 TON 4 Construct 6” DGA Subbase 329 CY 5 Excavation 767 CY 6 Raise Sanitary Manholes 25 EA 7 Reset water valve box 35 EA 8 Reset gas valve box 1 EA 9 Reset B Inlet with new N eco head 16 EA 10 Reset B Inlet With New Bicycle Safe Grate 2 EA 11 Traffic Markings Long Life Thermoplastic, White, 2’ Crosswalk 918 LF 12 Traffic Markings Long Life Thermoplastic, White, 2’ Wide Stop bar 75 LF 13 Traffic Markings Long Life Thermoplastic, Yellow, 4”, Wide Line 8,310 LF 14 Traffic Markings Long Life Thermoplastic, White Symbol 6 EA 15 Traffic Markings Long Life Thermoplastic, White, 4”, Wide Line 54 LF 16 Construct Concrete Handicap Curb Ramps 400 SY 17 Relocate Street Sign 3 EA 18 Remove Concrete Slab 81 SY 19 Install Truncated Domes 32 EA 20 Construct Belgium Block Curb 112 LF 21 Construct Concrete Curb 955 LF 22 Asphalt Price Adjustment 0 TON 23 Traffic Control 100 MH