The work to be completed under this contract consists of The Work to be completed under Contract No. BR-25-2024 shall include all work required for the complete replacement of ten (10) electrical substation cabinets for the traffic signal gantries on the Besty Ross Bridge. This includes removal and disposal of the existing cabinets, transformers, panelboards, switches, conduit, and associated electrical equipment; furnishing and installing new cabinets, transformers, panelboards, switches, conduit, and associated electrical equipment; and cleaning and painting the existing structural steel surfaces under the existing enclosures. The Contractor is responsible for coordinating and scheduling power outages and service interruptions, maintaining connections and electrical service to equipment outside the work area, and maintaining existing fiber optic facilities during construction.