Specifications include, but are not limited to: Washoe County Community Services Department (WCCSD) seeks a Construction Manager at Risk (CMAR) for pre-construction and construction management services for the Northern Nevada Adult Mental Health Campus Homeless Housing Project development and construction projects. The preconstruction services will be performed in conjunction with the scope of services being provided by the selected Architect (under a separate solicitation). The purpose of the project is the design and construction of a new regional fire station. This multi-phase, multi-GMP project encompassing 7 buildings and approximately 53,000 square feet. The preliminary project schedule includes initial facility assessment plans, programming, conceptual design, conceptual cost estimating and scheduling/construction planning to be completed by end of May 2019, and construction commencement per the phasing schedule in Section 5. These schedule assumptions are subject to change.