Specifications include, but are not limited to: The work to be performed under this Contract will generally consist of improvements on Maryland Parkway from 650 feet south of Tropicana Avenue to 200 feet north of Flamingo Road, a length of approximately one mile. The project includes installing a shared utility conduit duct bank to facilitate the undergrounding of overhead utility lines on the east side of Maryland Parkway. Transverse utility crossings requested by the utilities will be also installed. Existing overhead utility lines to be undergrounded include NV Energy, Cox, and Lumen. Work will include removal and reconstruction of bituminous pavement, curb & gutter, sidewalk, raised median, and pavement markings, and adjustment/relocations of existing utilities. The work also consists of miscellaneous removal and disposal and removal and salvage/replacement of designated items, traffic control, dust control, quality control, and other related items of work as specified and shown on the drawings.