Specifications include, but are not limited to:Phase 1, Stage 1: When constructing the permanent crossing pipe at Sta. 101+50, the Contractor may close Adams Central Ave., North of US-6 for 1 day. If this pipe is constructed prior to May 23, 2020, the road can only be closed on a weekend. Adams Central Ave cannot be closed May 9 & 10, 2020. Phase 1, Stage 2: Access to the private drive at Sta. 96+81 Lt. shall be maintained all through this phase. Phase 2: This phase must be completed and Adams Central Ave. open to normal two-lane, two-way traffic by August 9, 2020. Normal two-lane, two-way traffic is defined as uninterrupted traffic flow at the pre-construction posted speed limit. This phase cannot start prior to May 23, 2020.