Specifications include, but are not limited to: CLEARING AND GRUBBING A contractor may request notice to proceed and mobilize to perform clearing and grubbing, including removal of all logs, brush, and debris at the sites where the County has property rights prior to the nesting season. Per Section 108.02.04 calendar days will not be charged for this work item, and work at the site may be suspended following clearing and grubbing. Mobilization for clearing and grubbing will be considered subsidiary to that pay item, per Section 112. If clearing and grubbing is not performed prior to the start of Migratory Bird primary nesting season, generally occurring between April 1 and September 1, and permission to proceed has been given to the Contractor prior to September 1, the burden for coordination, requesting, and payment of the nesting survey shall fall on the County; with the Contractor responsible for clearing and grubbing of said site within 3 days of the survey, per Section 107.01.04.h.(3). Work shall follow Section 107.01.04.h. Migratory Birds except where specified herein.; USE OF EASEMENT AND RIGHT-OF-ENTRY DURING THE WORK The Contractor shall have the right to enter the property shown on the plans to accomplish the work in this Contract. It is the intent of this Special Provision to limit the Contractor's use of the existing and new right-of-way, temporary and permanent easements, or right-of-entry areas to those portions actually required to perform the work under this Contract as directed by the Project Engineer. The Contractor will not be permitted to disturb those areas which are not directly related to work required under the Contract. The Project Engineer will have the sole authority to determine what portions of the property may be disturbed.; INSTALLATION OF PERMANENT OR TEMPORARY EROSION AND/OR SEDIMENTATION CONTROL MEASURES The work covered in this section of the Special Provisions will include furnishing all labor, materials, equipment, fabrication, transportation, supplies, tools, supervision, and other incidentals necessary to provide and install the erosion and/or sedimentation control measures at locations called for in the proposal or as directed by the project engineer. The Contractor or his subcontractor will not be required to maintain the permanent erosion/sedimentation control measures on this project once they have been successfully installed and initial vegetative growth has been established and accepted by Lancaster County.; This specification covers three types of low VOC (volatile organic compounds), ready-mixed, one-component, 100% acrylic waterborne airfield and traffic marking paint. The paint is suitable for application on such traffic-bearing surfaces as Portland cement concrete, bituminous cement concrete, asphalt, tar, and previously painted areas of these surfaces. The paint may be used either alone or to bind reflective beads.