Specifications include, but are not limited to: • Remove existing submersible pumps and replace with new pumps in wetwell. Replace pump guide rails, cable, discharge piping and valves. • Rehabilitate wetwell interior and apply a new interior coating. • Remove and replace existing pump control instruments and control panel. • Install new pump control panel and reinstall transfer switch on new concrete pad with sun shade shelter over equipment. Install sidewalk from curb to concrete pad. • Grade adjustment of area around existing wetwell. • Provide temporary bypass pumping as required. Lake Hills Lift Station • Remove existing drywell mounted pumps and reinstall in existing wetwell. • Abandon existing drywell and salvage equipment. Backfill drywell with fill material as specified. • Rehabilitate wetwell interior with the application of a new liner. Remove all wetwell interior equipment and material including platform, vent piping, and railing. • Install pumps with guide rails, cables, discharge piping, and new valve & meter vault. • Replace wetwell lid including hatch and vent to accommodate the removal of the pumps. • Provide new valve and meter vault to include new valves, associated piping and fitting, and flowmeter. • Tie-in 10” force main from the new meter vault to existing lift station force main. • Replace station control panel and all electrical components excluding the existing generator automatic transfer switch. Electrical to include a new manual transfer switch and pin-and-sleeve connection for portable generator. • Remove existing jib crane and salvage to Owner. • Install new telemtry panel to include new PLC, UPS, level instruments, radio, and other equipment as detailed in bid documents. New pump soft starts to be installed in separate pump control panel. Install new antenna on existing roof mount. • Provide temporary bypass pumping as required.