Specifications include, but are not limited to: 1. Mechanical preparation/removal of existing epoxy floor and integral cove base. 2. Install by hand trowel method approximately 700 lineal feet of 6” epoxy cove base. 3. Patch and repair all cracks and delaminated areas. 4. Install approximately 250 square foot of Urethane Cementitious flooring in front of left and right side fryers to prevent thermal shock in these areas. 5. Create epoxy mortar slope under ice station machines to drain water to existing drain. 6. Install approximately 3,500 square foot of double broadcast decorative quartz epoxy flooring. 7. Apply polyurethane final topcoat to provide maximum chemical and scratch resistance. 8. Work on this project is time sensitive. Bidder will need to be able to start project on or before Monday, February 17th, with completion of the project no later than February 21st .