Specifications include, but are not limited to: Qualified Equipment with Operator Contractors to install up to (6) Concrete Box Culverts, weighing 22,000lbs each in Polk County, MO. Break up 17 yards of existing reinforced concrete and fill MoDOT dump trucks with the debris, to clean out area to lay concrete culvert boxes. Pickup and place each box culvert in the area MoDOT will be building a run off system. The Excavator or Crane lifting the Box Culverts will need to be able to extend out 15 foot to be able to place the boxes correctly. Contractor will then lay grade. Lump sum bid for all work identified in Scope of Work, labor hours, and mobilization should be included. MoDOT will supply all materials, dump trucks, road closure with traffic control established, and haul off all dump truck materials.