Specifications include, but are not limited to: 1.Contractor to provide a written schedule seven days prior to commencement of work. Schedule is to be monitored on a regular basis and updated copies, if required, are to be provided to the City monthly. 2.The Contractor is responsible for calling for utility locations prior to the start of the project. It shall be the Contractor’s responsibility to coordinate his work with any utility owner whom maybe in conflict with his work. No claims will be considered for extra compensation. 3.Installation & maintenance of erosion control devices to include daily covering of any disturbed areas with straw mulch as well as permanent grassing up to ¼ acre, in addition to sod placement.4.All testing of materials shall be in accordance with GDOT specifications.5.Disturbed areas shall receive permanent stabilization if not sodded or stabilized as directed by the Engineer. If grassing activities are not in season, then rye grass or grassing as directed by the Engineer will be utilized. Once grassing is in season, the area will be prepared and reseeded or sodded with permanent grassing by the Contractor. Sod is to be replaced “in kind”. 6.The Contractor is responsible for notifying all affected Property Owners prior to commencement of work with projected schedules of work activities along the frontage of the property.