Specifications include, but are not limited to: A. Item 1Project Schedule The Contractor shall submit a project schedule to RIPTA no later than two weeks after receiving RIPTA authorization to proceed with the project that includes the following: o The aboveground storage tank system and underground storage tank closure submittal dates. These submittals shall be made no later than four weeks after receiving RIPTA authorization to proceed with the project. o The aboveground storage tank system equipment ordering date o The aboveground storage tank system equipment delivery date o The underground storage tank system closure plan submittal date. o The aboveground storage tank installation project start date for onsite work. o The temporary fueling system start and completion date. The schedule shall include up to four weeks for temporary fueling operations. o The aboveground storage tank system operation start date for RIPTA fueling its fleet with the new aboveground storage tank system. o The aboveground storage tank installation project completion date for on-site work. The aboveground storage tank installation project completion date for on-site work shall be no later than six weeks after the project start date for on-site work. Landscape establishment and acceptance is anticipated to be later than six weeks after the aboveground storage tank installation start date. o The underground storage tank system closure start date. o The underground storage tank system closure completion date. The underground storage tank closure completion date shall not be more than two calendar weeks after the underground storage tank system closure start date. Landscape planting shall commence no later than two calendar weeks after the underground storage tank system closure start date. Landscape planting, establishment, and acceptance is subject to the RIDOT Blue Book requirements. o Petroleum impacted soil recycling/disposal shall be completed within 30 calendar days