Specifications include, but are not limited to: This project will replace the two low pressure steam boilers in the power plant, one of which has been condemned and tagged out by the boiler inspector, with a state‐of‐the‐art, high‐efficiency, condensing hot water boiler system. Steam piping within the boiler room would require replacement; however, all piping leading outside the boiler room is already hot water. To allow flexibility and longevity, the new system is expected to operate as two primary boilers, with a third as back‐up for the capacity on the coldest days, and will replace multiple heat exchangers, pumps, steam traps, valves, strainers, fittings and electrical components. Variable frequency drives will improve the efficiency of the new pumps. The existing glycol system will need to be pre‐tested, tested, cleaned and flushed. New building automation system controls will allow remote monitoring of the boiler plant.