The work for this project will generally consist of an urban street reconstruction which shall include the removal of the existing bituminous pavement, grading, concrete curb and gutter, storm sewer, sanitary sewer, water main, and bituminous paving. Ancillary work includes concrete flatwork, signing, seeding/restoration, and erosion control items. Major estimated project quantities include: Bituminous Pavement (All Mixes) 2,400 Ton Aggregate Base 3,520 Ton Rock Excavation 5,600 CY Concrete Curb & Gutter 5,220 LF Concrete Driveway Aprons 400 SY Sanitary Sewer Main 2,300 LF Sanitary Sewer Structures 9 EA Sanitary Sewer Laterals 35 EA Water Main 2,075 LF Water Laterals 37 EA Hydrants 3 EA Storm Sewer (All Sizes & Material) 3,080 LF Storm Sewer Structures (All Sizes) 25 EA