Exterior: 1. Construct a wooden ramp at front stoop to accommodate entry to home in a wheelchair. Include guard rail and handrail as required for handicap entry. Provide drawing of this ramp toy MLBO Building Official for pre-approval. (discuss with Toby at 320-630-2491). 2. Remove broken exterior windows in kitchen above the sink area. Provide and install new windows complete with repaired frame and sill complete. 3. Removal and disposal of construction debris and materials. Provide trash dumpster. 4. Complete replacement of 24 ga. insulated sectional overhead garage door and operator. 5. Use temporary jack posts to support the large exterior deck while installing new permanent footings and posts as the original posts and footings must be removed and replaced. The new replacement footings must be 60” deep and supported on a 4” x 12” concrete pad at the base of the footing. ADD (2) additional 4” x 4” posts and footings on the same front beam as the existing posts. The deck has settled and risen in the freeze thaw cycles and it is apparent the deck is not flat or level. The entire wood deck will be repaired as the configuration exists. 6. Provide and install new entry door lockset and deadbolt with four sets of keys. See existing and replace with same or use an acceptable manufacturer from the MLBO Spec. Book. Interior: 7. Remove old and Provide/Install (2) two new American Standard Cadet toilets. Inspect and repair any water supply, waste and vent in two bathrooms. Complete update of plumbing to be included to ensure proper new toilet function. Include all piping and water supply as necessary. 8. Remove bathroom flooring in two bathrooms and provide/install new Lifeproof Sterling Oak 6 mil x 8.7 in Wide x 48” L Click Lock Waterfroof from Home Depot vinyl plank bathroom flooring. Include underlayment and installation. Provide and install all new base and quarter round. 9. Tear out and dispose of the “skinny” linen closet located along the wet wall of the existing shower. Repair the walls by framing repairs and sheetrocking at this location and move wet wall to the left approximately 20”. The relocated (left) wet wall will be installed in the new framing and wall to fit. The shower will continue to operate with (2) two shower heads. There will be no linen closet with new low threshold, “ROLL-IN” style shower enclosure complete from wall to wall to be provided and installed by contractor. Move the floor drain to center if necessary and install a custom pan shower floor or a unitized shower enclosure. This pan must be sloped properly for the water to run into drain. Provide and install Handicap Bathroom and Shower Grab Bars. Provide and install backing throughout the entire Shower and Bathroom area to accommodate the grab bars and bathroom specialties. Provide and install a MultiFunction / Hand shower Package with Slide Bar, Hose, Holder complete with Rough-In Connection.