Specifications include, but are not limited to: Phase 1- ● (First week of July 2018)- Apply Round Up to all areas between fences. In the following weeks, touch up areas as needed. Removal of vegetation by chemical means requires proper certification. Contractor is responsible for all posting on the property and must provide proper proof of certification. Phase 2- ● (End of July 2018)- Roto-til entire area between fences. ● (Early August 2018)- Re Roto-til entire area between fences. Phase 3- ● (Mid August 2018)- Furnish and place approximately 400 cubic yards of topsoil to playing surface. Finish grade to facilitate a 10”-18” crown (approximately 1-1.9%) sloping uniformly from the center of the field to the sidelines, without pockets. The parallel sidelines should be level. Non-playing surface areas shall be graded to facilitate proper drainage throughout fenced in area. Grades to be deemed satisfactory by project manager upon completion.