The project involves the design and installation of a new fire suppression system to provide NFPA 13 compliance fire suppression coverage for all nine (9) stories of the residence tower at Lurie Terrace, based on the attached drawings and specifications. Modifications included as part of this project include but are not limited to: • New branch piping in hallways on each of the nine (9) floors (with flow sensor and inspector test ports). • Addition of suppression piping/sprinkler heads in all areas of the tower. • Installing flow and tamper switches as required. • All additional monitoring devices and interconnection to the fire alarm system as needed, including fire alarm modules, conduit, wiring, and programming. • Any required firestopping. • Architectural cut, patch, and paint as needed. All exposed piping must be cleaned to remove any oil residue, primed and painted. Contractor shall return to the site approximately 11 months after substantial completion to repaint any exposed piping that is showing evidence of drips or rust flashing through the finish paint.