2.1 Demolition of Structure: The Scope of Work (“Work”) for this RFP may include, but is not necessarily limited to: 2.1.1 Security: Provide site security for duration of project after notice to proceed is received and project work has begun. Coordination with the City of Alpena for planned Right-of-Way closures is required. City of Alpena Department of Public Works may be able to assist with barricades if needed with 72 hours advanced notice. 2.1.2 Mobilization: Includes all labor, equipment, materials, and incidentals to mobilize to the project site to perform the work, including but not limited to contractor office support, project meetings, site visits, site security, temporary controls and utilities, pre-work submittals, required permitting, personal protective equipment, disposal approvals, erosion controls, barricades, traffic control, trash disposal, cleaning, and demobilization. 2.1.3 Utilities: The City of Alpena has verified with 1) Alpena Power Company that power has been shut off and Alpena Power facilities removed; 2) Veolia that water has been shut off, and 3) DTE that gas lines have been cut and capped at the main. Contractor is required to properly cap the sewer line and cut and cap the water line; the water utility will ensure water shutoff at the street. Contractor is responsible for contacting Miss Dig prior to any demolition activity. 2.1.3.1 The contractor is responsible for providing water for dust suppression, if needed. Arrangements may be made with Veolia to utilize a nearby hydrant for water; water usage fees must be included in RFP submissions. 2.1.3.2 Contractor should arrange for alternate sources of power to operate needed equipment. Contractor has responsibility for confirming the disconnection of utilities prior to the start of site activities. 2.1.3.3 There are no restroom facilities at the project site. The contractor is responsible for providing access to restroom facilities for its workers. 2.1.4 Asbestos Containing Materials and Universal Waste: All asbestos/hazardous material and universal waste have been removed from the building and a passed clearance exam has been received from the environmental contractor. The ACM/Haz report is included in the Environmental Construction Management Plan from Otwell Mawby. 2.1.5 Soil Erosion: Contractor shall comply with the Natural Resources and Environmental Protection Act; Soil Erosion and Sediment Control, 1994 PA 451 Part 91 as amended. 2.1.5.1 Includes all application fees and obtaining a soil erosion and sedimentation control permit from Alpena County. Appendix C should be used as the site plan to pull the SESC permit. 2.1.5.2 Includes furnishing, installing, and maintaining as long as necessary and remove when no longer required, all necessary engineering controls to prevent erosion and control sedimentation of onsite soils. 2.1.6 Demolition: Includes all labor, equipment, materials, fees, permits, and incidentals needed to: demolish building, flatwork, and below grade structures associated with the building (including basement, foundations, footings, sumps, pits, vaults, etc.); transportation and disposal of all demolition debris; removal of concrete areas on site as specified below, private sidewalks; and utility disconnects, removal, abandonment or protection of buried underground utilities as specified. 2.1.6.1 Huron Engineering developed the demolition site plans which are included in this RFP as Appendix C; questions about the site plan should be directed to Becky Rivard at 989-356-6375. 2.1.6.2 A Demo Phase Environmental Construction Management and Due Care Plan has been created by Otwell Mawby due to previous fill materials brought on site, as well as an underground storage tank that was present at the site but was reported as removed. Moving of materials in these areas should be limited and should not be taken off site to other properties. Questions about the plan should be directed to James Jackson at 231-946-5200. 2.1.6.3 The cost to remove trees that are necessary to remove in order to facilitate demolition, or additional debris, should be included in the bid.