1. All site activities are to be coordinated with the DPW Commissioner or Designee. 2. The City will purchase and provide one (1) complete Burnham V1112 boiler and one (1) Power Flame power burner. The City will store these items near, but not inside the DPW Water Department boiler room located at 1 Franey Road, Somerville MA. 3. The City will conduct asbestos testing via a contracted environmental services firm on Wednesday, June 12th, 2025. The ACM test results will be issued as an addendum. 4. Contractor will: a. Obtain all required building permits from the City’s Inspectional Services Department prior to the beginning of the project, including hot-work permit and fire watch detail. Provide permit copies to the DPW Commissioner or Designee, prior to start of project. b. Disconnect and make safe, all utilities including city water, natural gas, electrical, and BMS controls systems. c. Demolish, remove, and dispose of the existing boiler flue piping off site. d. Disconnect the steam header and return piping only so far as needed for physical demolition of the old boiler and reinstallation of the new boiler. Temporarily support these items as needed. e. Carefully remove all boiler controls, safeties, limits, etc., and leave for the City f. Demolish existing Burnham V1112 boiler, power burner, and gas train and dispose of properly offsite. g. Provide all materials/supplies (including but not limited to pipe, valves, gaskets, caulking, sealants, etc.) that are needed to install the new boiler system.