The goal of this project is to remove suspect materials including ceiling panels, wall paneling, and insulation and replace them with new, clean finishes to create a habitable workspace. In Phase 1 of the project a new subpanel will be installed on the second floor of the building and temporary office space set up to allow for the relocation of the Library Director and other staff as needed to the second floor for the duration of the renovations. Phase 2 will include the demolition of wall and ceiling finishes in the basement, installation of new finishes, upgraded light fixtures, expanded window wells, and the creation of a separate office for the Library Director. Once the basement is completed the temporary office set up on the second floor will be removed. Electrical and communications improvements on the second floor will remain in place.