Specifications include, but are not limited to: It is the intent of DNR to replace the deteriorating bulkheads, storm drains, boat ramp with launching piers, and utilities within the State property. The Consultant shall provide recommendations on the type of design for the bulkhead replacements including but not limited to timber, steel, fiberglass polymer, etc. A. Bulkheads: 1. Steel Bulkheads – approximately 270 linear feet of existing steel bulkhead on the northwest area of the Marina near Pier A constructed in the 1960’s are to be replaced with bulkheads. There is no known record of the 1960’s plans from the Maryland Port Authority on this original construction. 2. Timber bulkheads in the vicinity of Piers B thru H constructed in the early 1980’s are to be replaced with bulkheads. Record Drawings associated with this construction are available as an attachment: Attachment No. 4 (F-20-792-016: Phase IV-A).