Specifications include, but are not limited to: 2.1. The following specification sections define the Work of this package: 2.1.1. Dredge Material Placement Site (DMP) Sediment and Erosion Control Plan 2.1.2. Mechanical Dredging Section 02230 2.2. Provide all labor, materials, tools, and equipment to complete Work. 2.3. Work with all contractors, utility companies, and the Town forces in the coordination and sequencing of the Work as part of the Contract to ensure that installation proceeds as efficiently as possible within the guidelines of the project schedule. 2.4. Excavate canals to the lines and grades indicated on the contract drawings. 2.5. Offload excavated material and transport to the DMP site located at 12008 St. Martins Neck Rd, Bishopville, MD. 2.6. Place excavated material at the DMP site to the lines and grades shown on the drawings.