Specifications include, but are not limited to: 2.3.1 Plan Three Complete Maryland YRBS/YTS Survey Cycles A. Submit Work Plan. The Contractor shall submit a draft Work Plan for the upcoming Survey Cycle to the Contact Monitor detailing the objectives, deliverable schedule, and required steps to achieve the goals of the YRBS/YTS project within 10 days of Contract award for the first Survey Cycle and by the end of September 2023 and 2025 for the second and third Survey Cycles. The Contract Monitor will review the draft Work Plan for acceptability and may request edits and further information, as needed. The Contractor shall discuss the Work Plan during the Kick-Off meeting for the first Survey Cycle, and during planning meetings in the fall/spring for the second and third Survey Cycles. The Contractor shall submit to the Contract Monitor the final Work Plan within 30 days after the Kick-Off meeting for the first Survey Cycle and 30 days after the planning meeting for the following Survey Cycles.