Specifications include, but are not limited to: Bridge construction at water crossings designated A-13-01 and B-02-01 at the T2 R9 Training Site. Project consists of the demolition of a temporary wooden bridge structure at crossing A-13-01 and the failed culvert at crossing B-02-01 and their replacement with steel bridge structures constructed using "stream smart' requirements as directed by the Maine Department of Environmental Protection, the Army Corps of Engineers and the Department of US Fish and Wildlife. Project also consists of the construction of a 24 foot wide asphalt apron on each side of the respective bridges (approx. 110 linear feet) as well as 4000 linear feet of 24 ft. wide gravel roadway on each side of the bridges past the asphalt aprons.