Specifications include, but are not limited to: The planned major turbine-generator outage is for fall of 2020. Major work scope items are as follows: Complete steam path inspection (rotor & diaphragms removed, blast cleaned, NDE, repairs as needed and realignment of components). All valves (5 control valves, 1 main stop valve, 1 main steam block valve, 1 main steam bypass valve, and 6 non-return valves, 6 cylinders and guides). Front standard governor table, control valve operating servo & pilot valve, main shaft pump and emergency trip assembly. Steam seal regulator. Main stop valve hydraulic actuator, Lube oil tank - all pumps, one auxiliary pump, turning gear pump and DC pump. Remove lube oil coolers, clean, inspect and reinstall. Remove Generator Cooler, clean, inspect, repair and reinstall. Inspect check valves in lube oil tank. Oil flush lube oil system. Remove and install generator field. Clean, inspect, service, and testing of generator miscellaneous components. Generator test & inspection with field removed. Seal oil system – inspect seal oil pumps & clean out seal oil float trap.