Specifications include, but are not limited to: Reclamation work consists of drilling and grouting 14 holes at a maximum depth of 40 feet. A temporary access road will be constructed. The waste material generated during project work will be used on site in the grading portion of the project boundaries. During the process of these construction activities, trees over 5 inches in diameter at breast height will not have to be removed in the AML problem area. A sediment and erosion control program, consisting of such measures as constructing hay bales/silt fence to be maintained throughout the life of the project and prompt re-vegetation using agricultural limestone, fertilizer, seed, and mulch will be implemented on all areas disturbed by this project. Entry to the work areas will be accessed by the county road, residential driveways, and residentially maintained yards. The entire project work area slated for any excavation has been previously disturbed by any or all of the following: coal mining operations, including mine drainage, timber operations, gas/ oil well development, residential development, road construction, and/or high velocity water flows associated with heavy rain events and flooding. These disturbances consist of significant upheaval, mixing, and removal of earthen material from deep excavation, grading, sub-surface drilling, fill material placement, and erosion. There should be no undisturbed earthen material to a depth of several feet at the areas slated for significant project-related construction activities. This project will include pre- and/or post- project maintenance and repair of existing previously constructed public county roads utilized during the construction of this project, which are administered by the county or local road authority. This construction activity will be conducted under the authority and supervision of the local public road authority and will consist of standard road construction practices appropriate to mitigate impacts to the local community from potential degraded road conditions in order to maintain public traffic safety.