Specifications include, but are not limited to: 1. Bid Package #26-1: Sitewide conduit; fiber optics; communications; site lighting; fire alarm system replacement. The Iowa Department of Administrative Services anticipates work beginning onsite for this bid package around September 30, 2019. The communications and site lighting shall be substantially complete by June 30, 2020. The fire alarm improvements will be phased, with portions of the project running concurrently with the work of a future bid issuance of Building Mechanical work. Refer to Section 00 3113 Preliminary Schedule for further information. 2. Bid Package #33-1: Sitewide water mains; building water services; tree removal; temporary tunnel shoring; PCC paving. The Iowa Department of Administrative Services anticipates tree removal beginning onsite around September 9, 2019. At the Contractor’s option, the water main and building water services work may begin in 2019 or 2020 and shall be substantially complete by August 7, 2020.