• Provide and install conduits between existing utility power pole and new concrete transformer pad and between transformer pad and DCFC charging stations • Form and pour a 6’ x 6’ concrete transformer pad (per Ames Electric specs) • Provide and install a 400A meter socket and a 400A breaker panel with 4 -125A breaker positions. To include mounting on a uni-strut frame. • Provide and install concrete foundation for 2 – DCFC charging stations • Install 2 - DCFC charging stations (provided by OWNER) • Provide and install wires between transformer, meter socket, breaker panel & DCFC charging stations • Make all wiring connections and terminations (unless noted on the drawings) • Provide and install protective bollards (where noted on drawings) • Restore site to original condition