The 2025 Asphalt Street Resurfacing Program project includes the hot mix asphalt (HMA) overlay of SW Ankeny Road from the west end of SW Twin Gates Drive to approximately 700 feet south of SW Snyder Boulevard and the patching, interlayer, and HMA overlay of NE Delaware Avenue from Four Mile Creek to approximately 600 feet south of NE 36th Street in the City of Ankeny. The construction improvements include approximately 225 CY of Class 13 excavation, 575 TON of HMA interlayer, 2,500 TON of HMA overlay, 1,800 TON of fiber-reinforced HMA overlay, 775 TON of granular shoulder, 1,150 SY of full depth patching, 150 STA of pavement markings, removal and replacement of sidewalk, temporary surface restoration, temporary traffic control, mobilization, and miscellaneous associated work necessary to complete the project.