Design includes installaƟon of an 8,000-to-12,000-gallon 100LL tank on a to be designed concrete pad adjacent the west apron, self-contained drainage, emergency fuel shut off and necessary stormwater miƟgaƟons and permiƫng, fiber installaƟon for Point of Sale system and vehicle gates 34 & 30, lighƟng and security camera needs. ConstrucƟon must be completed by September 1, 2026. The consultant will be expected to procure and or/prepare necessary survey; geotechnical engineering; any special environmental reporting; prepare detailed plans, specifications and cost estimate; print and provide drawings for 50%, for bid and for construction drawings; assist in securing construction bids, analyzing bid results; prepare and negotiate any change orders; represent the sponsor at preconstruction meeting; inspect work in progress no more than two on site visits; make final inspection and submiƫting report of the completed project to sponsor to include, but not limited to, any reports required by the Owner and any governing agency.